@startgantt
[Design phase/Prototype design] lasts 25 days
[Design phase/Test prototype] starts at [Design phase/Prototype design]'s end and lasts 20 days
[Design phase/Prototype completed] happens at [Design phase/Test prototype]'s end
[Production phase/Setup assembly line] lasts 15 days and starts at [Design phase/Prototype completed]'s end
[Production phase/Hire assemblers] lasts 10 days and ends at [Design phase/Prototype completed]'s end
[Production phase/Assemble first batch] lasts 3 days and starts at [Production phase/Hire assemblers]'s end
@endgantt